Setting the Project Path
The Project Path field in the Project Settings dialog allows you to set a default data path for the current project. This path is typically the root folder containing the input/output files for the current project.
NoteWhen the Project Path is not specified, LP360 automatically sets it to the folder of the first file being added. However, if the last folder is named "LAS", then it is set to one folder above that. |
How to set the project path
-
Open the Project Settings dialog as described in the Project Settings topic.
-
In the Project Path field, enter the default data path for the current project.
-
Click OK.